Forest Lake City Council members told staff they preferred a speedy resolution to the Daniel DePonti Airport’s paving project cost overrun situation as frustrations continued to mount with the engineering firm responsible for the disparity.
The council discussed the issue at a special Feb. 6 work session, which was attended by members of Dresel Contracting, a Chisago City-based firm that contracted with the city to perform excavation work last fall during the paving of the airport runway. As the project was nearing completion, the city was told by SEH, the engineering firm that designed the runway for the city, that an error in its estimation of how much fill would be needed to replace topsoil at the site had led to an overrun that would add hundreds of thousands of dollars to the project – 90 percent of which is likely to be paid by the Minnesota Department of Transportation Aeronautics