Amy Doeun
Wyoming Reporter
Road work was the big topic of discussion at the Sept. 5 Wyoming City Council meeting.broadstreet.zone(48036);
Resident Irv Hanson attended during the open forum at the beginning of the meeting. He was concerned about the speed limit on Goodview Avenue.
“Every town you go through, they turn the speed down – Rush City, Harris – we need to cut back on our speed limit,” he told the council. “I think our council needs to get behind it and do something on that. Whatever it takes to get the speed down. We should have some say as local residents.”
“We will look at that and see what we can do,” Mayor Lisa Iverson said.
Also on the agenda was payment two to Forest Lake Contracting for the 2017 street reconstruction project.
“They are making great progress,” City Engineer Mark Erichson said. “They are working ahead of the completion date, which was mid-October. They are